On site, the work inside the flare has been finalized from mechanical perspective, as scheduled. See the photo above.

At the RLT workshop, the pre-fabrication of piping is finalized and the pipes will be transported to Höganäs during the weekend. The RLT crew will start disassembling the existing piping from Monday. 

The secondary steel is now being galvanized and will be delivered by end of the next week to site. This new steel structure will be the first installation of the new part of the plant.

The main part of the work is moved from the workshop in Karlstad to site in Höganäs. It is essential to get up the secondary steel followed by the new piping and cyclones. Then the installation will be completed by insulation of all new piping as well as cabling for field instrumentation and electricity which will come later in March.

RLT Workshop in Karlstad, some of the piping and handrails for secondary steel before shipping.