During this past month we have, as communicated earlier, produced the first syngas at our plant in Höganäs. The syngas was of a very high quality, with the same high amount of hydrogen as seen before. This is a huge step for Cortus and our business partners.

Our focus is now towards milestone 3 (production of syngas during a period of 7 days).  There’s ongoing work to tune the dryer and pyrolysis so we can make the next milestone happen.

As many other companies we have also been affected by the Covid-19 pandemic, and we have relocated our personnel to fill up the gaps at our site in Höganäs. We are now back at full force in our test program. However, due to this fact we have postponed the completion of milestone 3 to May.